Particular Land Area (acres) Scheme Announcement Commencement of Construction Likely date of Completion No. of Dus Ave. Announced cost/sq ft (Rs) Revised Cost/sqft (Rs)
GREATER NOIDA HOUSING PROJECT 38 March 09 June 15 June 19 2130 3990 Cost to be revised after finalization of construction Agency

I. Administrative Approvals
  • Demand from GNIDA – It is to inform that after Allahabad High Court order, GNIDA demanded Rs.30,99,71,480/- towards additional compensation against the land allotment.
  • Environmental Clearance – Final term of reference submitted to the Environment Impact Assessment at Lucknow. Clearance letter is still awaited.
  • Aviation Clearance – All the documents submitted for clearance for AMSL height. Clearance still awaited.
  • Submission Drawings – All the submission drawings alongwith relevant fee with regard to the approval of plans by Statutory Authority have been submitted. Clearance awaited.
  • Prequalification of Contractors – Pre-qualification of the contractors completed, tenders issued to pre-qualified contractors and commercial bids expected to be received in the month of April 2015.
  • Proof Consultant for the quality assurance and vetting of structural drawings – Offers towards Proof Consultancy work including vetting of structural designs and drawings received from IIT, Roorkee and IIT, Delhi. Proposal towards award of consultancy shall be put up to Executive Committee, CGEWHO for approval.
II. Physical progress on Greater Noida Site
  • Dewatering – Slush from the site has been removed and all the dewatering work has been completed.
  • Land Survey – Contour survey and Survey of land completed.
  • Soil Investigation – Soil Investigation by IIT, Roorkee has been completed, interim report received and final report awaited.
Source: http://www.cgewho.in/gtnupdation.html

0 comments:

Post a Comment

Now Trending

34% DA Order for Central Govt Employees wef 01.01.2022 - Latest CG Employees DA Order Jan 2022

 DA Order for Central Government Employees from Jan 2022 - Finmin Order 2022 Latest CG Employees DA Order Jan 2022 Dearness Allowance payabl...

Disclaimer:

All efforts have been made to ensure accuracy of the content on this blog, the same should not be construed as a statement of law or used for any legal purposes. Our blog "Central Government Staff news" accepts no responsibility in relation to the accuracy, completeness, usefulness or otherwise, of the contents. Users are advised to verify/check any information with the relevant department(s) and/or other source(s), and to obtain any appropriate professional advice before acting on the information provided in the blog.

Links to other websites that have been included on this blog are provided for public convenience only.

The blog "Central Government Staff news" is not responsible for the contents or reliability of linked websites and does not necessarily endorse the view expressed within them. We cannot guarantee the availability of such linked pages at all times.

Any suggestions write to us
centralgovernmentnews@gmail.com